VOA Site B, Greenville, NC

I took a brief vacation last week along the coast of North Carolina. It was relaxing and fun to be sure. I was also aware of and slightly curious about the Voice Of America shortwave site, a slight distance inland in Grimesland, NC.  Thus, I made arrangements to visit the facility on my way home.  Chief Engineer, Macon Dail, was gracious enough to give us the guided tour.  The facility is an engineering marvel.  The scale and complexity are enormous.  The entire facility is scrupulously maintained.  Many of the transmitters and other equipment have been upgraded to make them more functional.   I tried to take meaningful pictures, but in many cases, they simply do not do justice.

Edward R Murrow Transmitting Facility, (VOA Greenville Site B) Grimesland, North Carolina

Officially known as the Edward R Murrow Transmitting Station of the International Broadcasting Bureau, VOA Site B was constructed in 1961.  Six of the eight shortwave transmitters are original to the construction of the building.  The other two (BBC SK55 and AEG S4005) were added in 1986.  All of the dipole curtain arrays, rhombics, transmission line, and antenna switching matrices are also original.  A few brief statistics about this site:

  • Land area is 2,715 acres (1099 hectares).
  • Over twenty-six miles (forty-two kilometers) of 300-ohm open transmission line rated at 500 KW.
  • Sixteen dipole curtain arrays, average antenna gain 17 dBi.
  • Twenty rhombic antennas, antenna gain 15 dBi.
  • Two of the dipole curtain arrays can slew azimuth and take off angle.
  • Three Continental Electronics 420A 500 KW Doherty modulated transmitters.
  • Three General Electric 4BT250A1 250 KW high-level plate modulated transmitters.
  • One Brown Boveri Company (BBC) SK55C3 500 KW PSM transmitter.
  • One AEG Telefunken S4005 500 KW PDM transmitter.
  • The antenna switch matrix connects any of the eight transmitters to any of the thirty-six antennas

While we were there, both of the newer transmitters were on the air, running at 250 KW.  The GE transmitters are used as needed and the Continentals are rarely used due to age, difficulty to tune, change frequencies, and gross power inefficiency.

The station staff has, out of necessity, fabricated some very cool upgrades to the transmitters and facility.  The first of which is the alarm annunciator, which is based on a Star Trek (Original Series) sound scheme.  Once or twice I heard the bridge general alarm go off, followed by a female voice stating the problem: “GB8, OFF AIR.”

Chief Engineer’s office.  NCC-1701; no bloody A, no bloody B, no bloody C, and no bloody D

The GE 250 KW transmitters have been retrofitted with a computer-controlled auto-tune system for frequency changes.  The antenna switch matrix controller has been replaced by a PLC-based system.  As the transmitters are so old, many of the transmitter-specific parts need to be machined or fabricated locally.  The rest of the transmitter parts are stocked in a large parts storage room, all of which are meticulously labeled and tracked.  The floors are waxed and spotless, there is no dust on the horizontal surfaces, the workshop is clean, tools are put away, grass and weeds are cut, etc.  All of these little details did not go unnoticed and indicated great pride by the staff in the facility itself.

The heart of the facility is the control room which consists of four rows of equipment racks and a central operating position elevated above floor level.  Arranged around that are the eight shortwave transmitters in two long transmitter galleries.

VOA Site B control room

From this point, the operator can view all of the transmitters in the two transmitter galleries.

Operating position

Around the control operator are arranged a series of computer monitors showing various station function status.

Transmitter modulation and status indicators
Antenna Matrix status and control
VOA transmitter control and status (center)
Audio monitoring router

The equipment is installed into the equipment racks by type; one rack contains the frequency generators for each transmitter, the next contains first-stage power amplifiers, the next contains audio processors and modulation monitors, etc.

Equipment racks and Shift Supervisor’s  office
Transmitter frequency generators
Audio processors, modulation monitors and patch panels
Backup audio feeds

The audio comes from the VOA studios in Washington DC via satellite. There are Comrex Access links as a backup and the Gentner EFT-1000s are used as a backup to the backup.  Prior to 1995, an eight-hop microwave system covering the 300-mile (483 KM) distance was used.

GE 4BT250A transmitter with computer-controlled tuning system installed

The station staff has created a computer-controlled tuning system for the GE transmitters. Each transmitter can change frequency several times a day, during each frequency change, all of the transmitter stages need to be retuned. When done by hand, this can take several minutes to accomplish. The computer system uses follow pots and microcontrollers to set the tuning elements to specific values. They can be touched up by hand if needed. A frequency change can usually be done in less than one minute.

GE 4BT250A transmitter
Your humble author and CE Macon Dail discussing the auto-tune system
GE 4BT250A auto-tune modification
GE 4BT250A IPA tube and input tuning.

The 2nd IPA and PA input tuning work the same way. The copper sleeve slides up and down over the coil to change resonant frequency. The vapor-cooled tube sits inside the tub at the top, anode facing down. These tuning sections are a mechanical nightmare according to Macon. One of the reasons why VOA site A was closed down was due to the frequent frequency changes at that site causing excessive wear and tear on the old GE transmitters. This particular transmitter was being repaired; the staff was rebuilding a tuning network bypass capacitor assembly

GE 4BT250A transformer vault

The GE transmitter transformers still contain PCBs. The plate transformers are in the back, basically pole transformers, one for each phase. Primary voltages are 4,180 volts, and secondary rectified voltages are 12 KVDC (PA plate supply)  and 15 KVDC (modulator plate supply).

Hallway and maintenance access to back of GE transmitters
AEG Telefunken S4005 500 KW transmitter on the air

While we were there, the newer transmitters were in operation transmitting Spanish language programming to Cuba on 13,605 KHz and 11,930 KHz.  Currently, the Greenville site is broadcasting mostly Spanish language programming with some English, French, and Bambara language programming for Africa.

A fact that does not escape the notice of the staff.

VOA transmitter gallery, showing transmitters GB8 through GB4
Continental Electronics 420A 500 KW Shortwave transmitter control and metering panel

The three Continental 420A transmitters (GB-1, GB-2, and GB-3) are essentially a pair of 250 KW amplifiers combined. As these are Doherty power amplifiers, frequency changes are very difficult to effect. These transmitters spend most of their time in backup service.

Electrical distribution panel

The antenna matrix building is very impressive. Routing eight 250 or 500 KW transmitters to 36 different antennas takes a bit of doing. Mechanizing that setup is no mean feat. The pictures I took of the antenna matrix building do not show the size and complexity of the system.

Transmission line between transmitter building and antenna matrix building

For that, we need a satellite photo:

VOA Site B antenna matrix building

Basically, the transmitter building is in the lower left-hand side of the picture. The transmission line go over to the antenna matrix building (looks like rectangular ductwork), then runs all the way to the back of the building. Each antenna transmission line comes into the building and runs to the other side. Pneumatic arms then couple the transmitter line to the antenna line. This is all controlled by a custom-made PLC and controlled by the operator from the main operating desk.

Custom-made antenna matrix control system
300-ohm open transmission lines
300 ohm open transmission lines

Some of these lines are very long but have low loss due to the air dielectric. The most used antennas are the dipole curtain arrays.

Dipole curtain arrays

These consist of a series of broadband dipole antennas arranged side by side and stacked three or four high. behind those antennas is a reflector screen. There are two curtain arrays that are slewable. The dipole antenna’s phase relationship to each other can be changed to adjust the takeoff angle and azimuth, thus giving optimum coverage to the targeted area.

Close up curtain array

In this picture, the dipole antennas are to the right. Behind them is the reflector screen, and behind that is the antenna feed system. Each antenna feed goes through the reflector screen to the center of the dipole antenna.

Each array requires four towers to support it.

Curtain dipole array supporting towers
Curtain dipole array supporting towers
Remote Antenna Switch.  Allows two antennas to use one transmission line.

The entire antenna field is viewable from an observation platform on the main building

Observation room
Entrance gate and slewable curtains in the background
Curtain arrays

The entire facility is very impressive. The truth is, I could have spent several more hours there, but I know that people have jobs to do and I felt that I had taken up enough time. We often forget in this country that not everyone in the world has access to the internet. Shortwave broadcasting has a long reach and is not subject to government-controlled firewalls or other forms of electronic censorship. Currently, the Greenville site is broadcasting mostly Spanish language programming with some English language programming for Africa. There are many areas in the world that are in political tension right now, some startlingly close to home. Places like Brazil, Argentina, and Venezuela have been in the news lately. I do not see a time when these long-reach broadcasting services will not be needed. Becoming a welcome source of good information for those affected people is good for brand USA. It would be money well spent to invest in a couple of new Continental 419H (still made in the USA) DRM-capable transmitters for this facility. While the old GE and Continental units are great, the time may come when they are really needed but unavailable due to being down for repair.

Special thanks to Macon Dail for his time, knowledge, and patience.

The Gates Air FAX-10, Numero Dos

This is the second Gates Air FAX-10 that I have installed. This one is in the shipping container transmitter site from the previous post of the same name.  In this case, we dispensed with the equipment rack that came with the transmitter and installed it in a standard Middle Atlantic rack.   The Harris rack configuration wastes a lot of space and since space is at a premium, we decided to do it our own way.

Gates Air FAX-10 in Middle Atlantic rack
Gates Air FAX-10 in Middle Atlantic rack

The bottom of the rack has the transmission line dehydrator. The top of the rack has the Dielectric A60000 series 1 5/8 inch coax switch, a Tunwall TRC-1 switch controller, and the Burk ARC-16 remote control.  I cut the rack panel top to accommodate the coax switch.  The racks were removed from an old studio site several years ago and have been in storage since then.

Gates Air FAX-10
Gates Air FAX-10

The Gates Air FAX-10 transmitter on the air, running a sports-talk format.

Dummy load and Broadcast Electronics FM10B transmitter
Dummy load and Broadcast Electronics FM10B transmitter

View from the other side showing the test load and BE FM10-B transmitter.  This transmitter had a problem that I have run into before with BE FM transmitters.  The jumper between the exciter and IPA had the wrong phase rotation causing reflected power.  I added a foot to its length and that problem disappeared.

Shipping Container transmitter site

Shipping container transmitter site from the early 1990's.
Shipping container transmitter site from the early 1990’s.

I do not particularly like these. I know, they are relatively inexpensive, easy to come by, easy to install, etc. However, a shipping container was not designed to house a transmitter, they have certain drawbacks. These are, in no particular order:

  • Air conditioning.  Using a traditional Bard-type equipment shelter HVAC unit requires cutting through a lot of fairly heavy gauge steel.  What’s more, the steel walls are uneven, requiring a filler.
  • They are by necessity, fairly narrow.  Arranging racks and transmitters along the length of the unit restricts access to either the front or the back of the equipment.  Meeting NEC clearance requirements for electrical panels, transfer switches, and disconnects can pose problems.
  • They are not very tall.  Mounting overhead equipment can be problematic as one does not want to drill through the top of the container.  Crosswise unistrut is one solution, but it lowers the overhead considerably.
  • Electrical work is slightly more dangerous.  Doing any kind of electrical work, troubleshooting, repairs, etc is a little more nerve-racking when everywhere around you is a metal surface at ground potential.
  • They are difficult to insulate against cold and heat.
  • The door-latching mechanisms bind, wear out or otherwise fail over time.

All of those things being said, I am now rebuilding a transmitter site in one of these shipping containers.

Inside view of shipping container transmitter
Inside view of shipping container transmitter site

Fortunately, the original electrical work was not bad.  The transmitter is a twenty-year-old BE FM10B, which will be retained as a backup.  The new transmitter is a Gates Air FAX-10.  We have installed several of these Gates Air transmitters in the last two years or so and they seem to be pretty solid units.  This is the second 10KW unit I have installed.

Gatesair FAX-10 transmitter in Middle Atlantic Rack

We decided to install the FAX-10 in a Middle Atlantic rack since we did not have a whole bunch of extra room for a separate transmitter rack.  The 1 5/8 inch coax switch is installed in the top of the transmitter rack along with a Tunwall TRC-1 switch control unit. The other rack will have the STL and all other ancillary gear.  My idea is to have nothing in between the door and the FM10B so it can be easily removed when that day comes.  Something, something about planning ahead since it will be likely myself removing the FM10B.

Commercial Radio Networks changing Satellites

Lockheed Martin A2100 series satellite
Lockheed Martin A2100 series satellite

Westwood One, Premiere, Skyview Networks, et al. will be changing their satellite from AMC-8 at 139° W to AMC-18/SES-11 at 105° W longitude.  More from AMC8transition.com. There are several considerations for this move:

  • Dish design and two-degree compliance
  • Obstacle clearance
  • Transponder frequencies
  • Timing

Two degree compliance is going to be an issue for many stations.  Those old 2.4 and 2.8 meter mesh dishes are going to have issues with 105º West because that is a very crowed part of the sky.  From New York, it looks something like this:

Satellite Longitude Inclination Azimuth Elevation Distance
TELSTAR 12 (ORION 2) 109.21° W 0.491° 227.46° 31.09° 38596.91 km
TELSTAR 12 (ORION 2) 109.21° W 0.491° 227.46° 31.09° 38596.91 km
MSAT M1 107.72° W 7.430° 231.14° 38.16° 38011.55 km
ANIK G1 107.33° W 0.013° 225.25° 31.96° 38518.62 km
ANIK F1 107.31° W 0.020° 225.22° 31.95° 38513.76 km
ANIK F1R 107.28° W 0.052° 225.22° 32.02° 38510.37 km
ECHOSTAR 17 107.11° W 0.019° 225.01° 32.08° 38503.29 km
AMC-15 105.07° W 0.025° 222.76° 33.28° 38400.67 km
AMC-18 104.96° W 0.027° 222.64° 33.34° 38400.16 km
GOES 14 104.66° W 0.198° 222.21° 33.38° 38394.57 km
AMSC 1 103.44° W 9.810° 228.37° 43.31° 37616.42 km
SES-3 103.01° W 0.041° 220.41° 34.42° 38307.12 km
SPACEWAY 1 102.90° W 0.032° 220.25° 34.43° 38299.87 km
DIRECTV 10 102.82° W 0.017° 220.17° 34.51° 38292.86 km
DIRECTV 12 102.78° W 0.035° 220.12° 34.50° 38292.93 km
DIRECTV 15 102.71° W 0.009° 220.05° 34.56° 38290.50 km
SKYTERRA 1 101.30° W 3.488° 219.07° 36.33° 38131.32 km
DIRECTV 4S 101.19° W 0.011° 218.24° 35.35° 38228.26 km
DIRECTV 9S 101.15° W 0.014° 218.18° 35.36° 38228.57 km
SES-1 101.00° W 0.016° 218.02° 35.45° 38217.56 km
DIRECTV 8 100.87° W 0.036° 217.88° 35.54° 38211.02 km

Generally speaking, dishes need to be 3.7 meters (12.14 feet) or larger to meet the two-degree compliance specification.  For many, this means replacing the current dish.  This is especially true for those old 10-foot aluminum mesh dishes that were very popular in the 90s because of the TVRO satellite craze.

If the existing dish is acceptable, then the next issue may be obstacle clearance.  Generally speaking, the 105-degree west slot (south of Denver) will be easier to see that the 139-degree west slot (south of Honolulu) for much of the United States.  Still, there may be trees, buildings, hills, etc in the way.  Site surveys can be made using online tools (dishpointer.com) or smartphone apps (dishalign (iOS) or dishaligner (Android)).  I have found that I need to stand in front of the dish to get the best idea of any obstacles.  While you are there, spray all the dish-holding hardware with penetrating oil like WD-40, Rostoff, or something similar.  Most of these dishes have not moved since they were installed, many years or decades ago.

Transponder frequencies will not be the same, so when the dish is aligned to the new satellite, those frequencies will need to be changed.  The network satellite provider will furnish this information when it becomes available.  This generally requires navigating around various menu trees in the satellite receiver.  Most are fairly intuitive, but it never hurts to be prepared.

The window of opportunity is from February 1, 2017 (first day of AMC-18) until June 30, 2017 (last day of AMC-8).  Of course, in the northern parts of the country, it may not be possible to install a new dish in the middle of winter.  It may also be very difficult to align an existing dish depending on how bad the winter is.  Therefore, the planning process should begin now.   A quick site evaluation should include the following:

Network Satellite Receive Location Evaluation

Satellite:

Satellite Location:

Dish is 2°compliant? (Y/N)

Distance to receiver location:

Dish Latitude:

Dish Longitude:

Dish Azimuth (T):

Dish Azimuth (M)

Dish Height AGL:

Dish Elevation:

Observed Obstacles:

(permanent or removable? Owned or not owned?)

Comments:

A .pdf version is available here. Based on that information, a decision can be made on whether or not to keep the old dish or install a new one.  We service about 25 studio locations and I am already aware of three in need of dish replacement and two that have obstructive trees which will need to be cut.  This work cannot start too soon.